Status Update - 3/14/19
	    March 14, 2019
	
    | Status Item | Current Status | Previous Status | Comment | 
| Schedule | green | yellow | |
| Resources | green | green | No resource availability issues | 
| Financials | green | yellow | CO submitted for $31,147 | 
| Quality | green | green | Quality metric remains green | 
| Project Issues | yellow | yellow | Banner/Axiom Integration data load is significantly delayed | 
| Key Deliverables | % | Comments | Timeline | 
| Requirement Sign-off | 100% | 12/14 | |
| Data Model/Mapping | 100% | 1/12 | |
| Build | 88% | Sprint 4 (3a): 3/4-3/15 | 3/28 | 
| Integration | 0% | UTSA reviewing query before load approval | 3/28 | 
| Training/UAT | 0% | Not Started | 4/22 | 
For the detailed March 14, 2019 status report, click here.